Newly reported records put dollar figures on power infrastructure for Google’s West Memphis data center, but Entergy says the first $716 million headline understated the full economics. Reports identified $526 million toward the Cypress Solar project and $190 million for transmission. Entergy later argued that the $526 million figure reflected only the upfront payment and […]
Source: finance.yahoo.com — article syndicated from the publisher’s feed; all rights remain with the original publisher.